Scope of works

What we built.

This package involves the construction of Improvement to Kurunegala - Narammala Road construction project.

The main construction works involved in these key activities.Roadway Excavation, Structural Excavation, Embankment Construction, Sub Base Construction, Dense Aggregate Base Construction, Asphalt Concrete Surfacing-Regulating, Asphalt Concrete Surfacing-Wearing, Structural Concrete Work.

Contract Number : RDA/RNIP/PRP2/C7-ii Original Contract Price : LKR 607,966,425.00 Employer : Road Development authority Engineer : xxxx Main Contractor : XI'AN DAGANG ROAD MACHINERY CO., LTD Location : Kurunegala District Construction Period : 20 Months Construction