Gampola – Pussellawa Road and Gampola – Nawalapitiya Road – Road
This package involves the construction of Balangoda – Gampola – Pussellawa Road and Gampola – Nawalapitiya Road – Road Construction Project. The main construction works involved in these key activities such as Soil Excavation – 96,048, 24.00 m3Rock Excavation – 28,180.50 m3, Concrete Work – 5,775.80 m3 .
- Contract Number : RDA/JBIC/RNIP/C1
- Original Contract Price : LKR 70 million
- Employer : Road Development Authority
- Engineer : Pacific Consultant International
- Main Contractor : CHEC(China Harbour Engineering Company)
- Location : Kandy District
- Construction Period : 24 Months Construction