Administration Building Complex, Hambantota

Successfully Completed the key part of civil work, which includes the construction of the main building and 25 nos. of accommodation units, the internal road network of the project, and Successfully supplied the concrete quantities for the whole project. The production and installation of timber doors and windows along with the fabrication and installation of aluminum doors, windows, and roof trusses were carried out successfully.  

  • Work Done: LKR 594 million
  • Employer: UDA, Sri Lanka
  • Main Contractor: Keangnam Enterprises Ltd.
  • Location : Hambanthota – Sri Lanka
  • Construction Period : 24 Months Construction + 12 Months Defects Liability